Project Summary
This Design/Build project replaced a custom AHU in an existing mechanical room that only had 9×9 ft opening for access. The entire project from demolition, installation, and startup was completed within ten days during Canada’s campus holiday shut down period. We relied heavily on BIM to plan out day-by-day activities in order to improve our overall construction duration.