300 Lakeside Boiler Replace

Oakland, CA
Project Summary

Phased boiler replacement project for a ~30 million BTU boiler plant that included removing (7) existing boilers & installing (6) new boilers over three phases with no downtime in a fully occupied building. Replacement of main HHW heat exchanger serving high rise loop. Upgrades to boiler flue system including draft assist flue fan & control dampers at each boiler. Controls upgrades including sequence of operations changes for improved plant energy efficiency.

Market Sectors
  • Commercial
  • Retrofit
Services
  • Mechanical
  • Plumbing
  • Engineering
  • Special Projects